Additions and Renovations

  • Conversion of King High School to King Middle School

    Once the new high school is completed, the current King High School campus will be converted to the new King Middle School.

     
    Conversion of KMS to Educational Support Building

    C.E. King Middle School will be repurposed for alternate district use(s). As the renovation of the existing C.E. King High School project develops, the district will continue to assess their district-wide facility needs.  More information will follow as the planning continues to progress. 
     

    Extended Parent Pickup Lanes

    Site renovations at Early Childhood Academies to allow additional on-site queuing for parent pickup.

    Schools Included:

    Stephanie Craven Early Childhood Academy
    Sheldon Early Childhood Academy


    Extended Student Loading/Unloading Canopies at Early Childhood Academies

    Extend canopies over existing walkways for student drop-off and pickup.

    Schools Included:

    Stephanie Craven Early Childhood Academy
    Cravens ECA Canopy Extension
     
    Sheldon Early Childhood Academy 
    Sheldon ECA Canopy Extension

    Buses/Student Mobility 

    Within the next five years, Sheldon ISD anticipates purchasing at minimum fifteen new school buses.

Timeline

  • Projects 2016 2017 2018 2019 2020
    1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
    Additions and Renovations
    Conversion of King H.S. to King M.S.
    Conversion of KMS to Educational Support Building    
    Extended Parent Pickup Lanes at ECAs
    Extended Student Loading/Unloading
    Buses/Student Mobility

    Legend: Planning Design Construction Completion